    North Slope oil production at risk if oil prices drop sharply

    SOURCE:  EIA

    Oil production on Alaska’s North Slope, which has been declining since 1988 when average annual production peaked at 2.0 million barrels per day, is transported to market through the TransAlaska Pipeline System (TAPS). Because TAPS needs to maintain throughput above a minimum threshold level to remain operational, its projected lifetime depends on continued investment in North Slope oil production that itself depends on future oil prices. In the Energy Information Administration’s (EIA’s) Annual Energy Outlook 2012 low oil price case, North Slope production would cease and TAPS would be decommissioned, which could occur as early as 2026.

    The 48-inch diameter, 800-mile long TAPS crude oil pipeline transports North Slope crude oil south to the Valdez Marine Terminal, where the oil is then shipped by tankers to West Coast refineries. TAPS is currently the only means for transporting North Slope crude oil to refineries and the petroleum consumption markets they serve.

    Low flow rates on crude oil pipelines can cause operational issues, particularly in the frigid Arctic. On June 15, 2011, the TAPS operator—Alyeska Pipeline Service Company—released the TAPS Low Flow Impact Study that identified the following problems that might occur as North Slope oil production progressively declines below 600,000 bbl/d, thereby resulting in declining TAPS throughput:

    • Potential water dropout from the crude oil, which could cause pipeline corrosion
    • Potential ice formation in the pipe if the oil temperature were to drop below freezing
    • Potential wax precipitation and deposition
    • Potential displacement of the buried pipeline due to soil freezing and thawing, as pipeline operating temperatures decline

    Other potential operational issues at low flow rates include: sludge drop-out, reduced ability to remove wax, reduction in pipeline leak detection efficiency, pipeline shutdown and restart, and the running of pipeline pigs that both clean and check pipeline integrity.

    The severity of potential TAPS operational problems is expected to increase as throughput declines; the onset of TAPS low flow problems could begin around 550,000 bbl/d, absent any mitigation. As the types and severity of problems multiplies, the investment required to mitigate those problems is expected to increase significantly. Because of the many and diverse operational problems expected to occur below 350,000 bbl/d, considerable investment might be required to keep the pipeline operational below this throughput level.

    Analysis of Alaskan production in the Annual Energy Outlook 2012 (AEO2012) assumed that the North Slope oil fields would be shutdown, plugged, and abandoned and TAPS would be decommissioned, when two conditions were simultaneously satisfied: 1) TAPS throughput was at or below 350,000 bbl/d and 2) total North Slope oil production revenues were at or below $5.0 billion per year. These conditions are satisfied only in the AEO2012 low oil price case, when North Slope oil production is shut down and TAPS is decommissioned in 2026.

    Related Articles

    CPG: $1.75B investment to serve Appalachian supply basins

    08/14/2014 Columbia Pipeline Group (CPG), a unit of NiSource Inc., reports a total of $1.75 billion in new investment in infrastructure that will enable it to transport up to 1.5 billion cubic feet per day of...

    BridgeTex Pipeline extends open season

    08/11/2014 Magellan Midstream Partners LP and Occidental Petroleum Corp. report that BridgeTex Pipeline has extended its supplemental open season for additional transportation commitments on the pipeline. Bin...

    Kinder Morgan to Expand Edmonton Terminal

    08/08/2014 Kinder Morgan reports that its joint venture has entered into additional firm take or pay agreements with oil majors sufficient to allow a planned expansion project to move forward by adding increm...

    BKEP to build Pipeline Project to Serve Eaglebine Crude Producers

    08/07/2014 Blueknight Energy Partners LP plans to build a major pipeline linking the emerging East Texas Eaglebine/Woodbine crude oil resource play to Oiltanking Houston, a crude oil and product terminal on t...

    Regency and AE-MIDCO Enter Into Joint Venture

    08/07/2014 Regency Energy Partners LP and American Energy – Midstream LLC (AE-MidCo) have entered into a joint venture agreement for the construction and operation of Regency’s previously announced Utica Ohio...

    More Oil & Gas Financial Articles

    CPG: $1.75B investment to serve Appalachian supply basins

    Thu, Aug 14, 2014

    Columbia Pipeline Group (CPG), a unit of NiSource Inc., reports a total of $1.75 billion in new investment in infrastructure that will enable it to transport up to 1.5 billion cubic feet per day of natural gas from Marcellus and Utica production areas to markets served by its Columbia Gas Transmission and Columbia Gulf Transmission pipeline systems. 

    BridgeTex Pipeline extends open season

    Mon, Aug 11, 2014

    Magellan Midstream Partners LP and Occidental Petroleum Corp. report that BridgeTex Pipeline has extended its supplemental open season for additional transportation commitments on the pipeline. Binding commitments are now due by 5 p.m. Central Time on Aug. 14.

    Kinder Morgan to Expand Edmonton Terminal

    Fri, Aug 8, 2014

    Kinder Morgan reports that its joint venture has entered into additional firm take or pay agreements with oil majors sufficient to allow a planned expansion project to move forward by adding incremental capacity of 110,000 barrels per day at the Edmonton Rail Terminal.

    BKEP to build Pipeline Project to Serve Eaglebine Crude Producers

    Thu, Aug 7, 2014

    Blueknight Energy Partners LP plans to build a major pipeline linking the emerging East Texas Eaglebine/Woodbine crude oil resource play to Oiltanking Houston, a crude oil and product terminal on the Houston Ship Channel, owned and operated by Oiltanking Partners LP.

    Regency and AE-MIDCO Enter Into Joint Venture

    Thu, Aug 7, 2014

    Regency Energy Partners LP and American Energy – Midstream LLC (AE-MidCo) have entered into a joint venture agreement for the construction and operation of Regency’s previously announced Utica Ohio River Project.

    Most Popular

    Oil & Gas Jobs

    Search More Job Listings >>
    Subscribe to OGFJ